Worcester and Birmingham Canal - History

History

The parliamentary bill permitting its construction was passed in 1791 empowering the company to raise £180,000 (£17.6 million as of 2012), through 1,800 shares at a cost of £100 each. It also allowed them to raise a further £70,000, if needed, amongst themselves or by the mortgage of tolls and rates. The Act also permitted the company to allow landowners on the line to build wharfs and wharfhouse, and if they refuse to, the company are allowed to if needed. A further Act of Parliament authorised the raising of £149,929 amongst themselves or through the creation of new shares. However, the company were unable to raise the full amount of money authorised by the second Act, and so another was passed allowing them to raise £49,680. Another Act was passed to obtain more money in 1808. This Act empowered the company to raise £168,000 through the creation of 4,200 shares at £40 each. A final Act was passed in 1815 after the company had purchased land for reservoirs, which was not permitted in the previous Acts. The Act permitted the company to sell the land and to pay a debt of £29,096 (£1,870,000 as of 2012), to the treasurers by September 29, 1815 as well, otherwise it would be taken out of the proceeds raised from selling the land.

The canal was surveyed by Josiah Clowes and John Snape. Its engineers changed often, and included Thomas Cartwright, John Woodhouse and William Crosley.

Construction of a barge-width (14 ft) canal began in 1792 from the Birmingham end, but progressed slowly. Selly Oak was reached in October 1795 and Kings Norton Junction by May 1796, meeting the new Stratford-upon-Avon Canal which had by then reached Hockley Heath. By March 1797 the 2726 yard (2493 m) Wasthill tunnel was open and the canal was trading to Hopwood. In 1807 the canal reached Tardebigge without the use of locks. The cost of building 14-foot (4.3 m) locks was too great so the 56 locks down to Worcester were built to the narrow 7-foot (2.1 m) specification, with the final two locks connecting to the Severn in Worcester being 14-foot (4.3 m) to allow river craft access to Diglis Basin.

The final 16 miles (26 km) was opened in December 1815. Plans to construct basins at Lowesmoor and Diglis were carried out eventually.

The Dudley Canal Line No 2 was built through the Lapal Tunnel to meet the canal at Selly Oak in 1798. After repeated collapses, the tunnel was finally abandoned in 1917 leaving a short stretch navigable between Selly Oak and a brick works at California until 1953, after which it was drained and filled in.

A major user of the canal was the Cadbury chocolate factories at Bournville and Blackpole, Worcester.

Read more about this topic:  Worcester And Birmingham Canal

Famous quotes containing the word history:

    Racism is an ism to which everyone in the world today is exposed; for or against, we must take sides. And the history of the future will differ according to the decision which we make.
    Ruth Benedict (1887–1948)

    My good friends, this is the second time in our history that there has come back from Germany to Downing Street peace with honour. I believe it is peace for our time. We thank you from the bottom of our hearts. And now I recommend you to go home and sleep quietly in your beds.
    Neville Chamberlain (1869–1940)

    Jesus Christ belonged to the true race of the prophets. He saw with an open eye the mystery of the soul. Drawn by its severe harmony, ravished with its beauty, he lived in it, and had his being there. Alone in all history he estimated the greatness of man.
    Ralph Waldo Emerson (1803–1882)