Reactor Data
The Virgil C. Summer Nuclear Generating Station consists of one operational reactor, with two additional units under construction.
Reactor unit | Reactor type | Capacity | Construction started | Electricity grid connection | Commercial operation | Shutdown | |
---|---|---|---|---|---|---|---|
Net | Gross | ||||||
Virgil C. Summer-1 | Westinghouse 3-loop | 966 MW | 1003 MW | 21 Mar 1973 | 16 Nov 1982 | 01 Jan 1984 | |
Virgil C. Summer-2 | AP1000 | 1117 MW | MW | 2017 (planned) | |||
Virgil C. Summer-3 | AP1000 | 1117 MW | MW | 2018 (planned) |
Read more about this topic: Virgil C. Summer Nuclear Generating Station
Famous quotes containing the word data:
“Mental health data from the 1950s on middle-aged women showed them to be a particularly distressed group, vulnerable to depression and feelings of uselessness. This isnt surprising. If society tells you that your main role is to be attractive to men and you are getting crows feet, and to be a mother to children and yours are leaving home, no wonder you are distressed.”