Swiftsure Class Submarine - Construction Programme

Construction Programme

Pennant number Name Hull (a) Hull builder Ordered Laid down Launched Accepted
into service
Commissioned Decommissioned Estimated
building cost
S126 Swiftsure 1 VSEL, Barrow. 3 November 1967 6 June 1969 7 September 1971 17 April 1973 1992 £37,100,000
S108 Sovereign 2 VSEL, Barrow. 16 May 1969 18 September 1970 17 February 1973 22 July 1974 11 July 1974 12 September 2006 £31,100,000
S109 Superb 3 VSEL, Barrow. 20 May 1970 16 March 1972 30 November 1974 29 November 1976 13 November 1976 26 September 2008 £41,300,000
S104 Sceptre 4 VSEL, Barrow. 1 November 1971 19 February 1974 20 November 1976 11 March 1978 14 February 1978 10 December 2010. £58,900,000
S105 Spartan 5 VSEL, Barrow. 7 February 1973 26 April 1976 7 April 1978 10 October 1979 22 September 1979 January 2006 £68,900,000
S106 Splendid (ex-Severn) 6 VSEL, Barrow. 26 May 1976 23 November 1977 5 October 1979 5 May 1981 21 March 1981 2004 £97,000,000

Read more about this topic:  Swiftsure Class Submarine

Famous quotes containing the words construction and/or programme:

    There’s no art
    To find the mind’s construction in the face.
    William Shakespeare (1564–1616)

    Bolkenstein, a Minister, was speaking on the Dutch programme from London, and he said that they ought to make a collection of diaries and letters after the war. Of course, they all made a rush at my diary immediately. Just imagine how interesting it would be if I were to publish a romance of the “Secret Annexe.” The title alone would be enough to make people think it was a detective story.
    Anne Frank (1929–1945)