Construction Milestones
Date | Milestone |
---|---|
29 January 1979 | Contract Award to Rockwell International's Space Transportation Systems Division. |
30 March 1980 | Start structural assembly of crew module. |
23 November 1981 | Start structural assembly of aft-fuselage. |
13 June 1983 | Wings arrive at Palmdale from Grumman. |
2 December 1983 | Start of final assembly. |
10 April 1984 | Final assembly completed. |
6 March 1985 | Rollout from Palmdale. |
3 April 1985 | Overland transport from Palmdale to Edwards Air Force Base. |
13 April 1985 | Delivery to Kennedy Space Center. |
12 September 1985 | Flight Readiness Firing. |
3 October 1985 | First flight. (STS-51-J) |
Read more about this topic: Space Shuttle Atlantis
Famous quotes containing the word construction:
“There is, I think, no point in the philosophy of progressive education which is sounder than its emphasis upon the importance of the participation of the learner in the formation of the purposes which direct his activities in the learning process, just as there is no defect in traditional education greater than its failure to secure the active cooperation of the pupil in construction of the purposes involved in his studying.”
—John Dewey (18591952)
Related Phrases
Related Words