RCDs are designed to disconnect the circuit if there is a leakage current. By detecting small leakage currents (typically 5–30 milliamperes) and disconnecting quickly enough (<30 ms), they may prevent electrocution. There are also RCDs with intentionally slower responses and lower sensitivities, designed to protect equipment or avoid starting electrical fires, but not disconnect unnecessarily for equipment which has greater leakage currents in normal operation. To prevent electrocution, RCDs should operate within 25-40 milliseconds at leakage currents (through a person) of 30 milliamperes, before electric shock can drive the heart into ventricular fibrillation, the most common cause of death through electric shock. By contrast, conventional circuit breakers or fuses only break the circuit when the total current is excessive (which may be thousands of times the leakage current an RCD responds to). A small leakage current, such as through a person, can be a very serious fault, but would not cause the total current to become high enough for a fuse or circuit breaker to break the circuit, let alone do so fast enough to save a life.
RCDs operate by measuring the current balance between two conductors using a differential current transformer. This measures the difference between the current flowing through the live conductor and that returning through the neutral conductor. If these do not sum to zero, there is a leakage of current to somewhere else (to earth/ground, or to another circuit), and the device will open its contacts.
Residual current detection is complementary to over-current detection. Residual current detection cannot provide protection for overload or short-circuit currents, except for the special case of a short circuit from live to ground (not live to neutral).
For a RCD used with three-phase power, all live conductors and the neutral must pass through the current transformer.
Read more about this topic: Residual-current Device
Famous quotes containing the words purpose and, purpose and/or operation:
“I think the worst thing this nation could do for humanity would be to leave any uncertainty as to our will, our purpose and our capacity to carry out our purpose.”
—Hubert H. Humphrey (19111978)
“A major misunderstanding of child rearing has been the idea that meeting a childs needs is an end in itself, for the purpose of the childs mental health. Mothers have not understood that this is but one step in social development, the goal of which is to help a child begin to consider others. As a result, they often have not considered their children but have instead allowed their childrens reality to take precedence, out of a fear of damaging them emotionally.”
—Elaine Heffner (20th century)
“Waiting for the race to become official, he began to feel as if he had as much effect on the final outcome of the operation as a single piece of a jumbo jigsaw puzzle has to its predetermined final design. Only the addition of the missing fragments of the puzzle would reveal if the picture was as he guessed it would be.”
—Stanley Kubrick (b. 1928)