Project Network

A project network is a graph (flow chart) depicting the sequence in which a project's terminal elements are to be completed by showing terminal elements and their dependencies.

The work breakdown structure or the product breakdown structure show the "part-whole" relations. In contrast, the project network shows the "before-after" relations.

The most popular form of project network is activity on node, the other one is activity on arrow.

The condition for a valid project network is that it doesn't contain any circular references.

Project dependencies can also be depicted by a predecessor table. Although such a form is very inconvenient for human analysis, project management software often offers such a view for data entry.

An alternative way of showing and analyzing the sequence of project work is the design structure matrix.

Famous quotes containing the words project and/or network:

    Although I mean it, and project the meaning
    As hard as I can into its brushed-metal surface,
    It cannot, in this deteriorating climate, pick up
    Where I leave off.
    John Ashbery (b. 1927)

    Parents need all the help they can get. The strongest as well as the most fragile family requires a vital network of social supports.
    Bernice Weissbourd (20th century)