A project network is a graph (flow chart) depicting the sequence in which a project's terminal elements are to be completed by showing terminal elements and their dependencies.
The work breakdown structure or the product breakdown structure show the "part-whole" relations. In contrast, the project network shows the "before-after" relations.
The most popular form of project network is activity on node, the other one is activity on arrow.
The condition for a valid project network is that it doesn't contain any circular references.
Project dependencies can also be depicted by a predecessor table. Although such a form is very inconvenient for human analysis, project management software often offers such a view for data entry.
An alternative way of showing and analyzing the sequence of project work is the design structure matrix.
Famous quotes containing the words project and/or network:
“Although I mean it, and project the meaning
As hard as I can into its brushed-metal surface,
It cannot, in this deteriorating climate, pick up
Where I leave off.”
—John Ashbery (b. 1927)
“Parents need all the help they can get. The strongest as well as the most fragile family requires a vital network of social supports.”
—Bernice Weissbourd (20th century)