Uncertainty in Project Scheduling
During project execution, however, a real-life project will never execute exactly as it was planned due to uncertainty. It can be ambiguity resulting from subjective estimates that are prone to human errors or it can be variability arising from unexpected events or risks. The main reason that PERT may provide inaccurate information about the project completion time is due to this schedule uncertainty. This inaccuracy is large enough to render such estimates as not helpful.
One possibility to maximize solution robustness is to include safety in the baseline schedule in order to absorb the anticipated disruptions. This is called proactive scheduling. A pure proactive scheduling is a utopia, incorporating safety in a baseline schedule that allows to cope with every possible disruption would lead to a baseline schedule with a very large make-span. A second approach, reactive scheduling, consists of defining a procedure to react to disruptions that cannot be absorbed by the baseline schedule.
Read more about this topic: Program Evaluation And Review Technique
Famous quotes containing the words uncertainty and/or project:
“You do not mean by mystery what a Catholic does. You mean an interesting uncertainty: the uncertainty ceasing interest ceases also.... But a Catholic by mystery means an incomprehensible certainty: without certainty, without formulation there is no interest;... the clearer the formulation the greater the interest.”
—Gerard Manley Hopkins (18441889)
“From a bed in this hotel Seargent S. Prentiss arose in the middle of the night and made a speech in defense of a bedbug that had bitten him. It was heard by a mock jury and judge, and the bedbug was formally acquitted.”
—Federal Writers Project Of The Wor, U.S. public relief program (1935-1943)