The super-columns are all nearly complete, with one crossbeam already in place, which will support the retractable roof, February 6, 2010
-
The site on July 2, 2010. The interior bowl is being completed on the west side, from a view at the outfield
-
The site on November 6, 2010. The main center roof being constructed
-
February 15, 2011
-
Adjacent parking structure on February 15, 2011
-
The site two weeks before completion of the final roof panel on March 13, 2011
-
The site on August 13, 2011 as seen from the Dolphin Expressway (SR 836) traveling east
-
Construction on August 25, 2011
Read more about this topic: Marlins Park
Famous quotes containing the words construction and/or gallery:
“No real vital character in fiction is altogether a conscious construction of the author. On the contrary, it may be a sort of parasitic growth upon the authors personality, developing by internal necessity as much as by external addition.”
—T.S. (Thomas Stearns)
“Each morning the manager of this gallery substituted some new picture, distinguished by more brilliant or harmonious coloring, for the old upon the walls.”
—Henry David Thoreau (18171862)