Light Rail - Costs of Light Rail Construction and Operation

Costs of Light Rail Construction and Operation

The cost of light rail construction varies widely, largely depending on the amount of tunneling and elevated structures required. A survey of North American light rail projects shows that costs of most LRT systems range from $15 million per mile to over $100 million per mile. Seattle's new light rail system is by far the most expensive in the U.S. at $179 million per mile, since it includes extensive tunneling in poor soil conditions, elevated sections, and stations as deep as 180 feet (55 m) below ground level. These result in costs more typical of subways or rapid transit systems than light rail. At the other end of the scale, four systems (Baltimore, MD; Camden, NJ; Sacramento, CA; and Salt Lake City, UT) incurred costs of less than $20 million per mile. Over the U.S. as a whole, excluding Seattle, new light rail construction costs average about $35 million per mile.

By comparison, a freeway lane expansion typically costs $1.0 million to $8.5 million with an average of $2.3 million per lane mile (a lane mile is a mile-long lane) for two directions. However freeways are frequently built in suburbs or rural areas, whereas light rail tends to be concentrated in urban space, where right of way and property acquisition is expensive. Similarly, the most expensive US highway expansion project was the "big dig" in Boston Massachusetts, which cost 200 million per lane mile for a total cost of 14.6 billion. Since a light rail track can carry up to 20,000 people per hour as compared with 2,000–2,200 vehicles per hour for one freeway lane, light rail is comparable in construction cost to freeways on a per passenger-mile basis. For example, in Boston and San Francisco, light rail lines carry 9,600 and 13,100 passengers per hour, respectively, in the peak direction during rush hour.

Combining highway expansion with LRT construction can save costs by doing both highway improvements and rail construction at the same time. As an example, Denver's T-REX (Transportation Expansion) project rebuilt interstate highways 25 and 225 and added a light-rail expansion for a total cost of $1.67 billion over five years. The cost of 17 miles (27 km) of highway improvements and 19 miles (31 km) of double-track light rail worked out to $19.3 million per highway lane-mile and $27.6 million per LRT track-mile. The project came in under budget and 22 months ahead of schedule.

LRT cost efficiency improves dramatically as ridership increases, as can be seen from the numbers above: the same rail line, with similar capital and operating costs, is far more efficient if it is carrying 20,000 people per hour than if it is carrying 2400. The Calgary, Alberta C-Train used many common light rail techniques to keep costs low, including minimizing underground and elevated trackage, sharing transit malls with buses, leasing rights-of-way from freight railroads, and combining LRT construction with freeway expansion. As a result, Calgary ranks toward the less expensive end of the scale with capital costs of around $24 million per mile.

However, Calgary's LRT ridership is much higher than any comparable U.S. light rail system at 300,000 passengers per weekday, and as a result its efficiency of capital is also much higher. Its capital costs were ⅓ that of the San Diego Trolley, a comparably sized U.S. system built at the same time, while by 2009 its ridership was approximately three times as high. Thus, Calgary's capital cost per passenger was much lower than that of San Diego. Its operating cost per passenger was also much lower because of its higher ridership. A typical C-Train vehicle costs only $163 per hour to operate, and since it averages 600 passengers per operating hour, Calgary Transit estimates that its LRT operating costs are only 27 cents per ride, versus $1.50 per ride on its buses.

Read more about this topic:  Light Rail

Famous quotes containing the words costs, light, rail, construction and/or operation:

    The real price of everything, what everything really costs to the man who wants to acquire it, is the toil and trouble of acquiring it.
    Adam Smith (1723–1790)

    Think what a mean and wretched place this world is; that half the time we have to light a lamp that we may see to live in it. This is half our life. Who would undertake the enterprise if it were all?
    Henry David Thoreau (1817–1862)

    For this is the mark of a wise and upright man, not to rail against the gods in misfortune.
    Aeschylus (525–456 B.C.)

    When the leaders choose to make themselves bidders at an auction of popularity, their talents, in the construction of the state, will be of no service. They will become flatterers instead of legislators; the instruments, not the guides, of the people.
    Edmund Burke (1729–1797)

    An absolute can only be given in an intuition, while all the rest has to do with analysis. We call intuition here the sympathy by which one is transported into the interior of an object in order to coincide with what there is unique and consequently inexpressible in it. Analysis, on the contrary, is the operation which reduces the object to elements already known.
    Henri Bergson (1859–1941)