Gotthard Base Tunnel - Specifications

Specifications

  • Length:
    • Western tunnel: 56.978 km (35.404 mi)
    • Eastern tunnel: 57.091 km (35.475 mi)
  • Total length of all tunnels and shafts: 151.84 km (94.35 mi)
  • Diameter of each of the single-track tubes: 8.83–9.58 m (29.0–31.4 ft)
  • Distance between cross passage tunnels: ca. 325 m (1,066 ft)
  • Maximum overburden: 2,500 m (8,200 ft)
  • Start of construction: 1993 (sounding drills), 1996 (preparations), 2003 (mechanical excavation)
  • End of construction: 2016
  • Commissioning: May 2016
  • Total cost: CHF 9.74 billion (as of October 2010) (US$10.1 billion)
  • Trains per day: 200–250
  • Electrification System: 15 kV, 16.7 Hz
  • Amount of excavated rock: 28,200,000 t (31,100,000 short tons; 27,800,000 long tons), (13,300,000 m3/17,400,000 cu yd, the equivalent of 5 Giza pyramids)
  • Number of tunnel boring machines (TBM): Four (two northbound from Bodio to Faido and Sedrun (Herrenknecht Gripper TBM S-210 “Sissi” and S-211 "Heidi") and two southbound from Erstfeld to Sedrun (S-229 “Gabi I” and S-230 “Gabi II”))
    • Total length: 440 m (1,440 ft) (including back-up equipment)
    • Total weight: 3,000 t (3,300 short tons; 3,000 long tons)
    • Power: 5 MW
    • Max. excavation daily: 25–30 m (82–98 ft) (in excellent rock conditions)
    • Total excavation length by TBM: about 45 km (28 mi) (for each tube)
    • Manufacturer: Herrenknecht, Schwanau, Germany
  • As of October 2010, 8 workers have died during construction.
  • 2004-2011 tunnel excavation:
Year Month Total excavated % of 151.84 km
2004 July 52.34 km/32.52 mi 34.1%
2005 June 74.59 km/46.35 mi 48.6%
2006 June 94.10 km/58.47 mi 61.3%
2007 June 103.67 km/64.42 mi 67.6%
2008 March 108.02 km/67.12 mi 70.4%
April 109.00 km/67.73 mi 71.0%
July 113.20 km/70.34 mi 73.8%
August 115.20 km/71.58 mi 75.1%
October 118.40 km/73.57 mi 77.2%
2009 January 124.00 km/77.05 mi 81.6%
March 127.30 km/79.10 mi 83.9%
May 131.00 km/81.40 mi 86.3%
June 133.00 km/82.64 mi 87.6%
July 134.80 km/83.76 mi 87.9%
August 136.60 km/84.88 mi 90.0%
September 137.30 km/85.31 mi 90.4%
October 138.60 km/86.12 mi 91.3%
November 140.00 km/86.99 mi 92.2%
December 141.38 km/87.85 mi 93.0%
2010 1 January 141.82 km/88.12 mi 93.4%
1 February 142.48 km/88.53 mi 93.8%
1 March 143.80 km/89.35 mi 94.7%
1 April 144.80 km/89.97 mi 95.4%
1 May 145.40 km/90.35 mi 95.8%
1 June 146.10 km/90.78 mi 96.2%
1 July 146.60 km/91.09 mi 96.6%
1 August 147.33 km/91.55 mi 97.0%
1 September 147.98 km/91.95 mi 97.5%
1 October 149.10 km/92.65 mi 98.2%
1 November 149.90 km/93.14 mi 98.7%
1 December 150.40 km/93.45 mi 99.0%
2011 1 January 150.49 km/93.51 mi 99.1%
1 February 150.77 km/93.68 mi 99.3%
1 March 151.26 km/93.99 mi 99.6%
1 April 151.70 km/94.26 mi 99.91%
1 May 151.75 km/94.29 mi 99.94%
1 June 151.82 km/94.34 mi 99.99%
1 July 151.82 km/94.34 mi 100%

Read more about this topic:  Gotthard Base Tunnel