Pacific Gas & Electric Company went through six years of hearings, referenda and litigation to have the Diablo Canyon plant approved. A principal concern about the plant is whether it can be sufficiently earthquake-proof. The site was deemed safe when construction started in 1968.

By the time of the plant's completion in 1973, a seismic fault, the Hosgri fault, had been discovered several miles offshore. This fault had a 7.1 magnitude quake 10 miles offshore on November 4, 1927, and thus was capable of generating forces equivalent to approximately 1/16 of those felt in the 1906 San Francisco earthquake.

The company updated its plans and added structural supports designed to reinforce stability in case of earthquake. In September 1981, PG&E discovered that a single set of blueprints was used for these structural supports; workers were supposed to have reversed the plans when switching to the second reactor, but did not. According to Charles Perrow, the result of the error was that "many parts were needlessly reinforced, while others, which should have been strengthened, were left untouched." Nonetheless, on March 19, 1982 the Nuclear Regulatory Commission decided not to review its 1978 decision approving the plant's safety, despite these and other design errors.

In response to concern that ground acceleration, or shaking, could cause spillage of submerged fuel rod assemblies which, upon exposure to air, could ignite, PG&E and NRC regulators insist that the foregoing scenario is anticipated and controlled for, and that there is no basis to anticipate spillage. Additional seismic studies are in process, though completion of those studies is not a condition precedent to re-issuance of the operating licenses for the two onsite units.

In October 2008, Unit 2 was taken offline for approximately two days due to a rapid influx of jellyfish at the intake.

The Nuclear Regulatory Commission's estimate of the risk each year of an earthquake intense enough to cause core damage to the reactor at Diablo Canyon was 1 in 23,810, according to an NRC study published in August 2010. In April 2011, in the wake of the Fukushima nuclear incident in Japan, PG&E asked the NRC not to issue license renewals until PG&E can complete new seismic studies, which are expected to take at least three years.

Read more about this topic:  Diablo Canyon Power Plant

Famous quotes containing the word history:

    As I am, so shall I associate, and so shall I act; Caesar’s history will paint out Caesar.
    Ralph Waldo Emerson (1803–1882)

    Free from public debt, at peace with all the world, and with no complicated interests to consult in our intercourse with foreign powers, the present may be hailed as the epoch in our history the most favorable for the settlement of those principles in our domestic policy which shall be best calculated to give stability to our Republic and secure the blessings of freedom to our citizens.
    Andrew Jackson (1767–1845)

    The awareness that health is dependent upon habits that we control makes us the first generation in history that to a large extent determines its own destiny.
    Jimmy Carter (James Earl Carter, Jr.)