Berkeley Pit - Important Dates

Important Dates

  • 1994 – September, EPA/DEQ issue Record of Decision (ROD) for Butte Mine Flooding Operable Unit.
  • 1996 – April, Montana Resources (MR) and ARCO divert Horseshoe Bend (HSB) drainage water away from Berkeley Pit to slow filling rate, per ROD.
  • 2000 – July, MR suspends mining operations due to high energy costs; HSB water allowed to flow back into pit, increasing pit filling rate.
  • 2002 – March, USEPA and Montana Department of Environmental Quality (MDEQ) enter into a Consent Decree with BP/ARCO and the Montana Resources Group (known as the Settling Defendants) for settlement of past and future costs for this site.
  • 2002 – Fall, USEPA and MDEQ issue order for Settling Defendants to begin design of water treatment plant for HSB water. Settling Defendants issue contract and begin construction of treatment plant.
  • 2003 – November, MR resumes mining operations.
  • 2003 – November 17, HSB water treatment plant comes on line slowing pit filling rate.

Read more about this topic:  Berkeley Pit

Famous quotes containing the words important and/or dates:

    I think the most important education that we have is the education which now I am glad to say is being accepted as the proper one, and one which ought to be widely diffused, that industrial, vocational education which puts young men and women in a position from which they can by their own efforts work themselves to independence.
    William Howard Taft (1857–1930)

    I never heard of an old man forgetting where he had buried his money! Old people remember what interests them: the dates fixed for their lawsuits, and the names of their debtors and creditors.
    Marcus Tullius Cicero (106–43 B.C.)