Berkeley Pit - Important Dates

Important Dates

  • 1994 – September, EPA/DEQ issue Record of Decision (ROD) for Butte Mine Flooding Operable Unit.
  • 1996 – April, Montana Resources (MR) and ARCO divert Horseshoe Bend (HSB) drainage water away from Berkeley Pit to slow filling rate, per ROD.
  • 2000 – July, MR suspends mining operations due to high energy costs; HSB water allowed to flow back into pit, increasing pit filling rate.
  • 2002 – March, USEPA and Montana Department of Environmental Quality (MDEQ) enter into a Consent Decree with BP/ARCO and the Montana Resources Group (known as the Settling Defendants) for settlement of past and future costs for this site.
  • 2002 – Fall, USEPA and MDEQ issue order for Settling Defendants to begin design of water treatment plant for HSB water. Settling Defendants issue contract and begin construction of treatment plant.
  • 2003 – November, MR resumes mining operations.
  • 2003 – November 17, HSB water treatment plant comes on line slowing pit filling rate.

Read more about this topic:  Berkeley Pit

Famous quotes containing the words important and/or dates:

    Men seldom persevere in a vocation unless they believe or can convince themselves that it is fundamentally more important than any other calling. Women are the same with their lovers.
    Friedrich Nietzsche (1844–1900)

    Nothing dates one so dreadfully as to think someplace is uptown.... At our age one must be watchful of these conversational gray hairs.
    Ruth Gordon (1896–1985)